A request by Ghana Grid Company Limited (GRIDCo) disclosed in a press release today said due to the construction of the road interchange at the ACP Junction, Pokuase, the capacity of the transmission network will be limited.
The statement signed by GRIDCo's Head of Public Relations, Albert Kwasi Quainoo added that the construction has taken out of service the 330kV Aboadze-Tema transmission line traversing the road to enable the contractor to divert the power line.
GRIDCo anticipates that the construction works would be completed by Tuesday, March 19, 2019.
"GRIDCo has accordingly advised Power Distribution Services (PDS) to redistribute loads at various Bulk Supply Points to ensure system stability. This may result in outages to some electricity consumers," the statement said.
Read the entire statement below;
Read Full Story